Juno Beach Distribution System Improvements (W1613)


Project Status: Contracts being Executed
​Project Value: $1,785,163
Anticipated Construction Start Date: January 2018

​Description: Many of the existing watermains and 2" galvanized services in the Juno Beach water distribution system were installed in the 1950's. An increasing number of line breaks due to age and condition of the pipe, valves, hydrants, and services in the area warrant their replacement. Existing backyard mains will be abandoned, replaced, and relocated to the road right of way to provide front yard services and adequate fire protection. Streets impacted by this project include: Neptune Road, Apollo Drive, Diane Lane, N. Juno Lane, Jupiter Lane, S. Juno Lane, Mars Way, Sunset Way, and Ocean Drive.

​Contact: Amanda Barnes, Assistant Director of Utilities, email or call 561-741-2537


RO-4 Well Improvements (W1515B)


Project Status Upcoming
Project Value: $657,885

Description: Construction of well mechanical, electrical, and instrumentation components for a Floridan Aquifer drinking water supply well located at the Town of Jupiter Water Treatment Plant.

Contact: Amanda Barnes, Assistant Director of Utilities, email or call 561-741-2537

Mobile Bed Absorber(MBA) Improvements & Degasifier Nozzle Replacements (W1503B)


Project Status: Upcoming
Project Value: TBD

Description: Demolish and construct new mechanical, structural, and instrumentation improvements to an existing hydrogen sulfide odor control system with two Mobile Bed Absorber (MBA) towers including small diameter PVC piping and fittings. Demolish and construct new distribution header piping and nozzles in three existing degasifiers at the Town's Reverse Osmosis Water Treatment Plant.

Contact: Amanda Barnes, Assistant Director of Utilities, email or call 561-741-2537