Posted on: January 12, 2017

Pine Gardens South Water Distribution Improvements

The Utilities Department has contracted with Blue Goose Construction to provide water distribution improvements in the Pine Gardens South subdivision during the next three months, January through March, 2017.  See the attached plan for water main, valve and fire hydrant replacements.  Following are our schedule of activities:

  • January 2017 to March 2017 Orange Drive Water Main Replacement
  • January 2017 through February 2017 Fire Hydrant Replacements
  • February 2017 to March 2017 South Loxahatchee Drive Valve Replacements

Please note we will have periodic traffic detours and water shut offs throughout the Pine Gardens South Subdivision.  There will be a minimum of 48 Hour notice to affected residents prior any water shut offs and all roadway detours, traffic and pedestrian access will be restored at the end of each day.  Access to properties will be provided at all times.  Please contact Steven Montemayor, Utilities Engineer with any questions or comments at 561-741-2710 (stevenm@jupiter.fl.us).


W1505 Pine Gardens South Water Distribution System Improveme

Facebook Twitter Google Plus Email

Other News in Road Construction & Traffic

construction

Road Closure Alert

Posted on: March 26, 2017
construction

Cinquez Park Canine Park

Posted on: March 23, 2017
road_work_ahead.png

Sidewalk Repairs - Bush Road

Posted on: March 1, 2017