Over the next three months, the Town will perform street resurfacing and roadway improvements at eight areas around Town. The project kicked off with the Riverside Drive Park Neighborhood on Monday, September 25. During each of the work periods detailed below, street parking will be prohibited between the hours of 7:30 am to 5:00 pm. Roads may also be limited to one lane, and flag personnel will be present.
Riverside Drive Park Neighborhood: From Monday, September 25 to Friday, November 3
Hammack Trace Neighborhood: From Monday, October 2 to Friday, November 10
Greenbriar Neighborhood: From Monday, October 9 to Wednesday, November 22
Hamptons Neighborhood: From Monday October 9 to Friday December 8
Cinquez Park: From Monday, October 16 to Wednesday, November 22
Holly Cove, Fernwood Creek and Greenwood Cove: From Monday, October 23 to Friday, December 22
South Loxahatchee Drive: From Monday, October 23 to Friday, December 29
Pine Gardens South Alleyways: From Monday, November 13 to Friday, December 29
For more information, call the Town's Engineering Department at 561-741-2467.